This afternoon I continued to work on the
placement and attachment of the oil cooler mounting section to the cooling
duct.  I moved the piece a fraction of an
inch to the left and drilled and installed a new clecoe.  I determined if I cut out a bit more of the upper
duct the transition between the pieces would be better.  I used the Dremel tool to make the
cutout. 
I used the angle grinder and a sanding disk
and sanded the area all around the cut where I will install fiberglass.  I mixed a batch of epoxy resin and cut some
fiberglass cloth.  I saturated the pieces
of fiberglass between 2-pieces of plastic. 
I  applied them to the perimeter
of the cutout and the cooler duct.  I
brushed on a layer of resin and will let it set until tomorrow.  I plan to retrim the opening and then remove the
duct and apply 2-layers of fiberglass on the inside.  Of course I will sand the contact area before
doing so.  I also plan to mix some epoxy
with flox and fill the inside voids before applying the cloth.  I need to make sure the new duct is
structurally sound before installing it on the cowling.